To maintain the overall health of our infrastructure and utility system. we have to occasionally close roads to perform upgrades. maintenance and replacements. The road closures below are scheduled but on occasion. we are forced to close roads to make unscheduled repairs to our equipment.
The below schedule and timeline are subject to change. Thank you for your patience as we work to provide you with safe and reliable electric and gas service.
Saturday, March 1, 2025
- Time: 7:00 A.M. – 5:00 P.M.
- Location FM3009 near Tuscan Hills Drive
- Zip Code: 78266
- Scope of Work: CPS Energy contractors and crews will be installing new wire at FM30098
- Traffic Control and Notifications: UCS Power will provide traffic control with maximum duration of the lane closure will be 15-minutes. Any subsequent lane closures can only happen after traffic congestion (from a prior lane closure) has cleared. There will be uniformed officers during this work.
- Outages: No Outages
- The Traffic Control Plan has been approved by TxDOT
Sunday, March 2, 2025
- Time: 6:00 A.M. – 3:00 P.M.
- Location: S Loop 1604 East of Campbellton Rd
- Zip Code: 78264
- Scope of Work: CPS Energy contractors and crews will be installing new overhead primary wire crossing S Loop 1604 E of Campbellton Rd.
- Traffic Control and Notifications: OSO Public Safety traffic control will be providing traffic control on the North and South bound side of Loop 1604 with 6 rolling traffic stops lasting up to 15 minutes, uniformed officers will be directing traffic.
- Outages: There will not be any outages during this procedure.
- The Traffic Control Plan has been approved by TxDOT
Monday, March 3, 2025 - Friday, March 7, 2025
- Time: 7:00 A.M. – 5:00 P.M.
- Location: TX-16
- Zip Code: 78264
- Scope of Work: CPS Energy contractors and crews will be transferring wire at the TX-16 crossing.
- Traffic Control and Notifications: Axis Power will provide traffic control with maximum duration of the lane closure will be 15-minutes. Any subsequent lane closures can only happen after traffic congestion (from a prior lane closure) has cleared. There will be uniformed officers during this work.
- Outages: There will not be any outages during this procedure.
- The Traffic Control Plan has been approved by TxDOT